Trail Maintenance Report

Date: May 15, 2010

Attendees: Russ 14 Ryan 12 Tom 14 Randall 15

Hours: 55

Category: 3N93, Reports

Russ, Tom, Randall and Ryan worked to divert and clear blocked stream crossings and cut back brush along 3N93. Major clearing of the stream crossing at the rock garden was performed to repair stream hydrology and divert the flow from entering directly into the rock garden. Thanks for all the hard work.